Service Type: Engineering Services
Surda Abu Qash Municipality provides the New Building Permit service to regulate construction activities and ensure compliance with approved laws and regulations.
- Required Documents:
1- Property tax clearance certificate for the applicant
2- Proof of land ownership (periodic power of attorney, legal sale agreement, or court affidavit to preserve partners’ rights)
3- Certified land survey plan (issued within the last 6 months)
4- CD
5- Copy of the owner’s ID
- Processing Time:
30 working days from the date of submitting all required documents
- Fees:
According to plot classification and construction location
- Legal Reference:
• Building and Planning Regulations for Local Authorities (2011)
• Structural plan of Sarra–Abu Qash Municipality approved by the Ministry of Local Government
- Procedure:
1- Receive the building permit application
2- Pay file opening fees
3- Review documents by the Engineering Department
4- Conduct a site inspection
5- Prepare official letters for approval of plans from Health, Antiquities, and Land Authority
6- Submit stamped plans
7- Await approvals from relevant authorities
8- Receive approved and signed plans from official entities
9- Prepare the full file and submit it to the Building and Planning Committee for decision (approval / rejection / modification)
10- Await committee meeting
11- Committee reviews the file; if approved, fees are calculated
12- Notify the citizen of the decision
13- Collect fees and issue the permit
14- Approve and sign the permit
15- Archive the licensing file
16- Deliver the permit to the citizen
- Implementing Entity:
Engineering Department